The formula

Target/day = operators x working minutes x efficiency / SMV.

Worked example

Operators: 30, Working minutes per day: 480 min, Garment SMV: 8.5 min, Expected efficiency: 60 %. Result: Target per day = 1,016 pcs; Target per hour = 127 pcs.

Assumptions

  • Steady-state target; learning-curve days run below it.

This calculator is the single-use version of what Intelactory runs across every style.

Costing sheets, line plans, dye recipes and packing lists that compute themselves from your real orders, with the numbers connected end to end.