Sewing Line Target Calculator
Daily and hourly line target from manpower, working minutes, SMV and expected efficiency.
Target per day
1,016pcs
Target per hour
127pcs
The formula
Target/day = operators x working minutes x efficiency / SMV.
Worked example
Operators: 30, Working minutes per day: 480 min, Garment SMV: 8.5 min, Expected efficiency: 60 %. Result: Target per day = 1,016 pcs; Target per hour = 127 pcs.
Assumptions
- Steady-state target; learning-curve days run below it.