Target per day
1,016pcs
Target per hour
127pcs
The formula
Target/day = operators x working minutes x efficiency / SMV.
Worked example
Operators: 30, Working minutes per day: 480 min, Garment SMV: 8.5 min, Expected efficiency: 60 %. Result: Target per day = 1,016 pcs; Target per hour = 127 pcs.
Assumptions
- Steady-state target; learning-curve days run below it.
Read the guide
In the platform
Intelactory computes line efficiency from the output and attendance each line records, and forecasts capacity conflicts across lines and factories.