Order Lead Time Estimator

Rough calendar lead time for an order from stage durations, with fabric and trims procured in parallel.

Lead time

57days

Material critical path

30days

The formula

Lead time = max(fabric, trims) + cutting + sewing + finishing + inspection + buffer.

Worked example

Fabric in-house: 30 days, Trims in-house: 20 days, Cutting: 3 days, Sewing: 12 days, Finishing & packing: 5 days, Final inspection: 2 days, Buffer: 5 days. Result: Lead time = 57 days; Material critical path = 30 days.

Assumptions

  • Fabric and trims procured in parallel; production stages sequential.
  • A quick estimator, not a TNA; overlapping production needs a real plan.